Blog

Fast Lanes and Speed Bumps on the Road to PJM Governance Reform

Electricity , Institutions & Governance

Electricity costs and demand are rising in PJM. FERC wants major reforms, but no one agrees on how. Is PJM really "ungovernable"?

Squabbling. Infighting. Accusations of incompetence and being held hostage to “special interests.” Hearings with made-for-TV moments and threats of endless litigation. This might sound like Congress, but this is where the PJM Interconnection–the world’s largest competitive market for electric energy–and its regulator, the Federal Energy Regulatory Commission (FERC), have now found themselves.

Once a power grid with an energy surplus, PJM now finds itself struggling to meet growing electricity demand from data centers while managing costs. The looming threat of blackouts is not due to incompetent staff, any physical fuel shortage, a supply chain failure, or a geopolitical issue.

In a word, the problem with PJM is now “governance.”

The governance of PJM involves four parts. FERC ultimately approves PJM’s planning and market designs. An independent Board of Managers decides which designs to file with FERC (“filing rights” under Section 205 of the Federal Power Act). Membership formulates design ideas and votes on which to send to the Board. In some cases, the Board is obligated to file the design approved by the Members. Finally, outside stakeholders influence governance through PJM’s management or through FERC.

Two governance elements are unique to PJM among RTOs. First, PJM’s Members have, in some cases, the authority to bypass the Board and file with FERC even if the Board disagrees, thereby limiting the Board’s power to make unilateral changes.  Second, the states within the PJM market have a limited governance role, and their representative, the Organization for PJM States (OPSI), has no voting rights in member deliberations. Consumer advocates, who represent a small minority of PJM’s voters, are the closest proxies for state interests.

Governance in PJM exploded when data-center energy demand drove some of PJM’s market prices so high that Pennsylvania’s governor filed a complaint with FERC. When PJM’s members were asked to consider twelve different proposals for integrating data centers into PJM’s markets, all twelve failed, leaving PJM’s management and Board scrambling.  This past summer, the Trump administration sounded the alarm as PJM’s impasse threatens the goal of U.S. dominance in artificial intelligence.

In the wake of these developments, FERC took the unusual step of opening up a complaint against PJM. Not because of high market prices per se, but because of PJM’s governance. It convened a proceeding in July in which FERC grilled PJM staff and stakeholders alike and opened a mediation process to develop a set of governance reforms.

On September 30, PJM convened its members to discuss three proposals, which included an array of different governance reforms:

  • Shifting some member filing rights to the PJM Board;
  • Giving the states, through OPSI, authority to make their own competing filings with FERC if they disagreed with PJM’s filings;
  • Reforming the nomination process for PJM’s Board to include input from states;
  • Changing the power of member voting;
  • Increasing transparency around Board decision-making (which is now mostly confidential)

The proposals had some critical differences. PJM’s proposal would have shifted more authority to the Board and would have made the membership voting process merely advisory. The proposal from PJM’s Membership was open to the concept of shared filing rights with states and PJM’s Board, but would not relinquish any existing authority.

PJM’s Membership soundly supported its own proposal, rejecting PJM’s and the third proposal from a group of consumer advocates.

The immediate next step is for PJM’s Board to consider the member’s proposal and how to respond. The Board faces a number of unappealing options.

PJM could file the Member’s proposal with FERC. The Commission seems unlikely to favor a proposal featuring a more limited role for the states and may come across as incrementalism rather than real reform.

PJM could file its own proposal independent of the members’ vote. This might make FERC happier, but it would likely face lawsuits from the membership, which has filing rights over the voting process. However, PJM’s staff has suggested that the September 30 vote was more along the lines of a poll and would not bind the Board’s decision-making.

PJM could continue working with its members and stakeholders to develop a solution. FERC, however, seems to have grown impatient with PJM’s ability to act quickly.

PJM could effectively file a complaint against itself with FERC, perhaps arguing that its governance process is so broken that only an Order from FERC can fix it.

FERC is not in an easy situation either. While legal scholars debate this, FERC sees itself constrained by prior court decisions not to directly order specific changes in RTO governance. FERC could do so following an administrative trial, but those can be long processes and there is no guarantee that any solution would not wind up back in court. PJM’s governance crisis is immediate.